One 2 One Call Centres - Dundee and Merthyr Tydfil
We specialise in fast-track projects, and have completed numerous call centres. One to One being a 61,000 sq. ft. call centre which was completed within a 14 week programme.
|
 |
Central Quay -Phase 2
Another fast-track project where, with great assistance from our fully trained site labour, we completed an office block of some 79,000 sq. ft. within a 14 week programme, the first fix works being completed within 7 weeks, our installation team working 12 hour shifts, 7 days a week.
|